Development History Register

Old Forge Development History Register

Explore Old Forge's dated development record, including filings, engineering work, field investigations, meetings, site visits, and stakeholder consultation. Each entry identifies the event or document and its supporting source.

Each entry identifies what occurred, when it occurred, and the organizations documented in the record. Attendance or participation is reported as a historical fact and is not characterized as an endorsement unless an authorized source expressly states otherwise.

26 of 26

Declaration of Intention filed for Old Forge Borehole reclamation and pumped storage

REA submitted a Declaration of Intention to FERC seeking a federal jurisdictional determination for the proposed Old Forge Borehole reclamation and pumped-storage concept.

Organizations: Renewable Energy Aggregators / Federal Energy Regulatory CommissionRelated material: FERC Docket DI18-2

REA completed the Old Forge Borehole mine-pool review

REA completed a technical review addressing the Borehole discharge, mine-pool geometry, historical flow and chemistry information, mine-water resource considerations, and subsidence-related questions.

Organizations: REARelated material: REA, Old Forge Bore Hole Mine Pool Review, March 8, 2018

FERC issued a jurisdictional determination in DI18-2

FERC issued an order addressing the jurisdictional question raised in the Declaration of Intention for the Old Forge concept.

Organizations: Federal Energy Regulatory CommissionRelated material: FERC Docket DI18-2

Old Forge multi-stakeholder site visit

A documented site visit was conducted at the Old Forge Borehole. The attendance record identifies representatives associated with the Susquehanna River Basin Commission, Tetra Tech, EPCAMR, the Lackawanna River organization represented by Bernie McGurl, the U.S. Fish and Wildlife Service, Black & Veatch, Ames Construction, Voith Hydro, Bostonia Partners, Linde Construction, and Renewable Energy Aggregators.

Organizations: REA, SRBC, Tetra Tech, EPCAMR, LRCA, USFWS, Black & Veatch, Ames Construction, Voith Hydro, Bostonia Partners, Linde ConstructionRelated material: Project attendance records, photographs, and correspondence

DOI and U.S. Fish and Wildlife Service project-footprint correspondence

Federal resource-agency correspondence addressed the project footprint and environmental review context.

Organizations: U.S. Department of the Interior / U.S. Fish and Wildlife ServiceRelated material: DOI letter dated August 14, 2018

Voith ternary pumped-storage technology description entered the project record

A technical description addressed ternary pumped-storage equipment and operating concepts.

Organizations: Voith HydroRelated material: Project record

PJM system impact study issued

PJM issued a generation interconnection system impact study for a project queue position.

Organizations: PJM Interconnection / PPL Electric UtilitiesRelated material: PJM Queue AE1-059 system impact study

Voith equipment proposal issued

Voith issued a project equipment proposal and technical package for ternary pumped-storage units.

Organizations: Voith HydroRelated material: Project record

PADEP dam-safety pre-application meeting

Participants discussed proposed dams, reservoirs, preliminary engineering, permit requirements, and follow-up work.

Organizations: Pennsylvania Department of Environmental Protection / REA / Project TeamRelated material: PADEP meeting minutes and presentation

Geotechnical field investigation conducted

The program included borings, rock coring, soil and rock sampling, groundwater observations, laboratory testing, downhole testing, televiewer work, and geophysical investigation for reservoirs, gatehouses, powerhouse, and related facilities.

Organizations: Haley & Aldrich and subcontractorsRelated material: Final Preliminary Geotechnical Data Report

RETTEW aquatic-resource field investigation

RETTEW investigated streams, wetlands, and related aquatic resources in the study area.

Organizations: RETTEW Associates, Inc.Related material: RETTEW planning document and wetland memorandum

Wetland and stream investigation memorandum issued

RETTEW documented its aquatic-resource investigation and identified aquatic-resource features for preliminary project planning.

Organizations: RETTEW Associates, Inc.Related material: Wetland and Stream Investigation Memorandum, September 21, 2020

Timber rattlesnake habitat evaluation memorandum issued

RETTEW evaluated potential habitat considerations for timber rattlesnake in the project area.

Organizations: RETTEW Associates, Inc.Related material: Project record

Cultural-resources desktop review completed

RETTEW reviewed available cultural-resource information and identified preliminary sensitivity considerations for project planning.

Organizations: RETTEW Associates, Inc.Related material: Project record

Final preliminary geotechnical data report issued

The report consolidated the field investigation, laboratory testing, geophysics, groundwater, and subsurface interpretation for the project area.

Organizations: Haley & AldrichRelated material: Final Preliminary Geotechnical Data Report, November 3, 2020

Preliminary multi-discipline design and design-basis package issued

Coordinated design-basis, civil, structural, hydraulic, architectural, mechanical, and electrical materials were issued at approximately 30 percent design completion.

Organizations: Kleinschmidt AssociatesRelated material: Preliminary design drawing package and design basis document

Congressional abandoned-mine-reclamation event at the Old Forge Borehole

U.S. Representative Matt Cartwright hosted a public event at the Old Forge Borehole concerning Bipartisan Infrastructure Investment and Jobs Act funding and abandoned-mine-land reclamation. The public invitation identified Representative Cartwright, Bobby Hughes, R. John Dawes, Bob Durkin, and Lindsay Griffin as speakers. The Mayor of Duryea Borough attended the event in person. Contemporaneous news coverage reported on the Borehole, federal reclamation funding, and REA's proposed treatment and energy initiative. Attendance does not constitute endorsement unless an authorized source expressly states otherwise.

Organizations: U.S. Representative Matt Cartwright / Mayor of Duryea Borough / REA / Invited speakers and participantsRelated material: Public event invitation; contemporaneous news coverage

Two-unit 184 MW ternary single-line diagram entered the record

A single-line diagram reflecting the current two-unit 184 MW equipment concept was issued.

Organizations: Voith Hydro / Project TeamRelated material: Project record

High-level project risk summary completed

A risk review addressed key technical, regulatory, commercial, schedule, and development considerations for project advancement.

Organizations: Kleinschmidt AssociatesRelated material: Project record

Old Forge key stakeholder meeting and site visit

REA organized a site visit and technical meeting addressing the Old Forge Borehole, proposed lower-reservoir area, pumped-storage engineering, equipment, water treatment, abandoned-mine reclamation, environmental matters, and regional infrastructure. The agenda and correspondence identify participation or planned participation by representatives associated with REA, Kleinschmidt, Voith, PADEP, the Bureau of Abandoned Mine Reclamation, Tetra Tech, the Susquehanna River Basin Commission, the Lackawanna River Conservation Association, Knight Piésold, the Scranton Chamber of Commerce, congressional staff, and other project participants.

Organizations: REA, Kleinschmidt, Voith, PADEP, Bureau of Abandoned Mine Reclamation, Tetra Tech, SRBC, LRCA, Knight Piésold, Scranton Chamber of Commerce, congressional staffRelated material: Meeting agenda and correspondence

Lackawanna River Conservation Association follow-up on Borehole treatment and community benefits

Written commentary addressed the Borehole, treatment scale, multiple AMD sources, long-term operations, residuals, and community benefits.

Organizations: Bernie McGurl / Lackawanna River Conservation Association / REARelated material: Email dated May 12, 2022

PADEP multi-program PACT consultation

Applicable PADEP programs discussed permitting and technical requirements for the project.

Organizations: Pennsylvania Department of Environmental Protection / REA / Project TeamRelated material: PADEP consultation record

Notice of Intent and Pre-Application Document filed and served

REA filed and served the current NOI and PAD for Project No. P-15411, establishing the current public-process record.

Organizations: REA / FERC / StakeholdersRelated material: FERC Docket P-15411

Public filing raised questions concerning transmission corridor and property activity

A filing asked whether reported transmission and property activity related to P-15411.

Organizations: Public commenter / FERCRelated material: FERC eLibrary, Docket P-15411

Additional public comment filed in P-15411

A public comment entered the current docket.

Organizations: Public commenter / FERCRelated material: FERC eLibrary, Docket P-15411

Corrected independent grid screening completed

The September 9, 2026 screening record adds an independent assessment of Old Forge's generation, pumping, and reactive-power settings. It identifies location-dependent electrical effects and a focused next step: utility validation and comparison with a defined transmission or operating alternative. The work builds on, and remains distinct from, the project's historical PJM interconnection studies.

Organizations: Independent / REA development recordRelated material: Public screening summary — /engineering-studies#september-2026-screening